Image #264 (2.75" x 4.5"): "4-24-29. Driving piles for falsework footings. Anchor Pier 10."; Image #266 (2.75" x 4.5"): "Progress in Cooper River. Looking north."; Image #265 (2.75" x 4.5"): "4-24-29. Typical group of piles pulled together for bracing & cutting off."; Image #267 (2.75" x 4.5"): "4-26-29. Loading cypress piles from car to lighter."
Image #268 (2.75" x 4.5"): "4-26-29. Twelve carloads of chords for Cooper River Span. 3 cars per load of 3 - 90 ft. chords."; Image #270 (2.75" x 4.5"): "4-26-29. Line of bottom chords - Spans 10, 11, & 12. From top of Pier 10, looking east."; Image #269 (2.75" x 4.5"): "4-26-29. 90 ft. Chord sections for Anchor Arm. Lightest chords 15 tons each and heaviest, 36 tons."; Image #271 (2.75" x 4.5"): "4-28-29. Looking up the West Approach toward Town Creek Span. Street paved (see #36)."
Unnumbered Image (5" x 7"): "Progress in Cooper River, April 26, 1929 at 4:30 P.M. material tower at Pier 13 (right) is erecting viaduct traveler 'C' to complete the east Approach."